Pharmacy Hall Addition News

Monday, August 11, 2008

Many construction activities are just wrapping up to complete phase one of the demolition process:
  • Mass demo of 120PH Lecture Hall
  • Installation of structural modifications
The “Sitework Phase” will continue through September and will include:
  • Installation of the telecommunications duct bank
  • Bulk excavation with debris being sorted and disposed of according to LEED requirements
  • Installation of sheeting and shoring for the protection of surrounding areas and to support the perimeter of the excavation site
Impact of Current Work:
  • For the duration of this construction project, the pathway along Pine Street will be located along the old Dental School building (Hayden Harris Hall). It will be open from 6 a.m. to 6 p.m.and will be illuminated with site lighting.
  • The Pharmacy Hall lounge, kitchenette, and canteen/copy area will remain available to students this semester.
In mid-September, more underground work will begin, which will take about 4 weeks:
  • Installation of Chilled Water lines
  • Installation of Ice Storage lines
LEED Efforts (Leadership in Energy and Environmental Design) during this phase of the project include:
  • Materials & Resources Credit: Construction Waste Management
  • Our goal is to divert 50-75 percent of the non-hazardous construction, demolition, and land-clearing debris from disposal in landfills and incinerators, to redirect the recyclable recovered resources back to the manufacturing process, and redirect reusable materials to appropriate sites.
  • Recycled materials include concrete, plastic, brick, metal, acoustical tile, glass, carpet, insulation, and gypsum wallboard.
  • It is not possible to reuse a significant amount of debris for the new construction. However, many of Pharmacy Hall's original bricks can be used to restore that side of the lounge when the atrium is built.