Wednesday, March 25, 2009

Concrete was poured this morning for the first portion of the Addition’s second floor. Pump trucks arrived at 5 a.m., and the process was finished by 10 a.m., with approximately 350 cubic yards of concrete placed.





Thursday, March 05, 2009

The concrete for the second half of the first floor elevated slab was poured between 5 and 8 a.m. this morning. Framing for the second floor is taking place, with concrete scheduled to be poured at the end of March.