Monday, November 17, 2008

More pictures of concrete being poured.

Thursday, November 13, 2008

Half of the building's mud mat has been poured (pictures below). This mat seals the site so that the reinforcing steel bar (rebar) does not get muddy. It also provides a surface for attaching the bentonite waterproofing. Once the waterproofing material is in place, the bottom rebar will be installed. After that, drain piping will be installed. Next, the top bars will be installed and then 42" of concrete will be poured. Columns and foundation walls will follow.

Monday, November 03, 2008

Dewatering of the site continues with 695,000 gallons of water being pumped from the site in the first two days of the process. Water-proofing is being done below grade, and the grounding grid is being laid in preparation for the foundation being poured.