Pharmacy Hall Addition News

Monday, April 26, 2010

Below is a general synopsis of the work going on throughout the entire project:

- Corridor flooring is installed on the 4th-7th floors and is currently being installed on the 2nd and 3rd floors.
- Ceiling grid is complete on the 2nd-7th floors with the exception of the bridges and elevator lobbies.
- Plumbing fixtures are being installed in the bathrooms from the 4th-6th floors.
- Lab casework is installed on the 4th and 5th floors and is currently being installed on the 6th floor.
- Write-up areas are installed on the 4th and 5th floors.
- The entire building with the exception of the bridges and elevator lobbies, has received the first two coats of finish paint.
- Partial lights are currently being installed on all floors with the lab lights being energized and active on the 4th and 5th floors.
- Grading and concrete base for the new sidewalks are currently being installed on the north and west exteriors.



This image shows the new fire pump room, which is the pump that provides water to the sprinkler system if there should be a fire.

Porcelain tile is being installed in the 3rd floor primary corridor.

Counter tops are being installed on the 4th floor lab casework.

This image shows break room casework installed on the 6th floor in room N607.

This image shows a 7th floor lab.The flooring and the steel support frames for lab casework is installed.

Monday, April 26, 2010

The external elevator/constuction hoist was removed between April 19 and April 22. Whiting and Turner is now using the inside elevator to allow for completion of the final curtain wall/window elevation that will be installed at the former location of the construction hoist. Removal of the external construction hoist also permits the interior completion of the break rooms which are situated in the southeast corner of the Addition.


The work being performed on the existing building is replacement of the precast concrete panels. These new panels match the color and texture of the precast concrete panels of the Addition. Also, landscaping work is being conducted along the MLK side of both buildings. Current work in this regard is the grading of the dirt sub-grade for the new sidewalks, as well as the removal of the earthwork spoils that are in the location of what will be the new planting bed/landscape area.


Friday, April 09, 2010



As spring blooms, the construction of the Pharmacy Hall Addition progresses. The atrium is completely enclosed and the glass-walled stair case is under construction. Ceiling grids are in, flooring is being installed and painting is almost complete. Laboratory casework has been laid out on three floors. The first replacement panel of the existing Pharmacy Hall exterior has been installed on the MLK side of the building. The new entry was is also progressing. The network should be up by the second week in May. Final punch out inspections for each floor have been scheduled for late May through mid-June. Furniture delivery and installation is scheduled for July 7, 2010 and will take until August 1, 2010 to complete.

Below to the left is the view from the 5th floor conference room. Below to the right is the new Leavitt Garden that looks out onto the Biopark.