Pharmacy Hall Addition News

Friday, April 09, 2010



As spring blooms, the construction of the Pharmacy Hall Addition progresses. The atrium is completely enclosed and the glass-walled stair case is under construction. Ceiling grids are in, flooring is being installed and painting is almost complete. Laboratory casework has been laid out on three floors. The first replacement panel of the existing Pharmacy Hall exterior has been installed on the MLK side of the building. The new entry was is also progressing. The network should be up by the second week in May. Final punch out inspections for each floor have been scheduled for late May through mid-June. Furniture delivery and installation is scheduled for July 7, 2010 and will take until August 1, 2010 to complete.

Below to the left is the view from the 5th floor conference room. Below to the right is the new Leavitt Garden that looks out onto the Biopark.