Below is a general synopsis of the work going on throughout the entire project:
- Corridor flooring is installed on the 4th-7th floors and is currently being installed on the 2nd and 3rd floors.
- Ceiling grid is complete on the 2nd-7th floors with the exception of the bridges and elevator lobbies.
- Plumbing fixtures are being installed in the bathrooms from the 4th-6th floors.
- Lab casework is installed on the 4th and 5th floors and is currently being installed on the 6th floor.
- Write-up areas are installed on the 4th and 5th floors.
- The entire building with the exception of the bridges and elevator lobbies, has received the first two coats of finish paint.
- Partial lights are currently being installed on all floors with the lab lights being energized and active on the 4th and 5th floors.
- Grading and concrete base for the new sidewalks are currently being installed on the north and west exteriors.
This image shows the new fire pump room, which is the pump that provides water to the sprinkler system if there should be a fire.

Porcelain tile is being installed in the 3rd floor primary corridor.

Counter tops are being installed on the 4th floor lab casework.

This image shows break room casework installed on the 6th floor in room N607.
.JPG)
This image shows a 7th floor lab.The flooring and the steel support frames for lab casework is installed.
- Corridor flooring is installed on the 4th-7th floors and is currently being installed on the 2nd and 3rd floors.
- Ceiling grid is complete on the 2nd-7th floors with the exception of the bridges and elevator lobbies.
- Plumbing fixtures are being installed in the bathrooms from the 4th-6th floors.
- Lab casework is installed on the 4th and 5th floors and is currently being installed on the 6th floor.
- Write-up areas are installed on the 4th and 5th floors.
- The entire building with the exception of the bridges and elevator lobbies, has received the first two coats of finish paint.
- Partial lights are currently being installed on all floors with the lab lights being energized and active on the 4th and 5th floors.
- Grading and concrete base for the new sidewalks are currently being installed on the north and west exteriors.
This image shows the new fire pump room, which is the pump that provides water to the sprinkler system if there should be a fire.
Porcelain tile is being installed in the 3rd floor primary corridor.
Counter tops are being installed on the 4th floor lab casework.
This image shows break room casework installed on the 6th floor in room N607.
This image shows a 7th floor lab.The flooring and the steel support frames for lab casework is installed.